The project was taken on from another design team on demand of the community of Halstenbek , because the costs were getting out of control.
There were efficient moderations at the beginning to fast track the needs and constraints of all stakeholders, and to define the essential conditions: angular arrangement as the enclosure of the playing area, spacious entrance hall, pitched roof to fit into the environment, the possibility that the roof could be equipped with a solar system and a budget of less than 3 million €.
These requirements were met by a complete revision of the draft. The roof construction of prefabricated wall panel components was chosen as an inexpensive, quick way to implement the unusual roof shape. The project is clearly still under the given budget and has been completed on time in spite of adverse weather conditions.
↧